Klondike 1 Wind is a 26.0 MW wind interconnection project in Wasco, Oregon with a current status of operational. It is proposed to connect at Interconnection is BPA's De Moss 115 kV Substation.

26.0 MWCapacity
OperationalStatus
ORMarket
WindTechnology

Project facts

Canonical nameKlondike 1 Wind
Queue IDG82
Statusoperational
Source statusENERGIZED
MarketOR
TechnologyWind
Capacity26.0 MW
StateOregon
CountyWasco
Point of interconnectionInterconnection is BPA's De Moss 115 kV Substation
Requested (queue) date2001-10-18
Proposed in-service date
Operational date2002-09-01
Withdrawn date
DeveloperNorthwestern Wind Power, LLC
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata