KY Queue Project LGE-GIS-2021-013 — Battery in Hardin, Kentucky

KY Queue Project LGE-GIS-2021-013 — Battery in Hardin, Kentucky is a 120.0 MW battery interconnection project in Hardin, Kentucky with a current status of suspended. It is proposed to connect at Hardin County 69 kV Substation.

120.0 MWCapacity
SuspendedStatus
KYMarket
BatteryTechnology

Project facts

Canonical nameKY Queue Project LGE-GIS-2021-013 — Battery in Hardin, Kentucky
Queue IDLGE-GIS-2021-013
Statussuspended
Source statusLGIA signed, currently suspended
MarketKY
TechnologyBattery
Capacity120.0 MW
StateKentucky
CountyHardin
Point of interconnectionHardin County 69 kV Substation
Requested (queue) date2021-03-29
Proposed in-service date2025-05-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerLouisville Gas & Electric and Kentucky Utilities Energy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectsuspendedhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: lgeku-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata