Laramie-Sidney 345 kV (GEN-2022-032)

Laramie-Sidney 345 kV is a 155.0 MW solar interconnection project in Kimball, Nebraska with a current status of withdrawn. It is proposed to connect at Laramie-Sidney 345 kV.

155.0 MWCapacity
WithdrawnStatus
NEMarket
SolarTechnology

Project facts

Canonical nameLaramie-Sidney 345 kV
Queue IDGEN-2022-032
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologySolar
Capacity155.0 MW
StateNebraska
CountyKimball
Point of interconnectionLaramie-Sidney 345 kV
Requested (queue) date2022-06-22
Proposed in-service date2028-02-11
Operational date
Withdrawn date2023-06-23
Developer
Utility / transmission ownerBEPC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.