Nebraska Interconnection Projects
interXdata tracks 744 interconnection projects in Nebraska representing 84,355 MW of requested capacity. The dominant technology by capacity is Wind. The most active counties are Lancaster, Douglas, Lincoln.
744Total projects
89Active
366Operational
282Withdrawn
84,355 MWRequested capacity
13,383 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 250 | 38,932 MW |
| Solar | 114 | 16,549 MW |
| Other | 177 | 13,937 MW |
| Gas | 160 | 10,031 MW |
| Battery | 41 | 4,526 MW |
| Solar+Battery | 2 | 380 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Lancaster | 57 | 5,565 MW |
| Douglas | 24 | 1,789 MW |
| Lincoln | 20 | 4,671 MW |
| Custer | 19 | 1,390 MW |
| Banner | 18 | 7,196 MW |
| Cass | 17 | 3,669 MW |
| Otoe | 16 | 1,734 MW |
| Sarpy | 15 | 1,139 MW |
| Madison | 15 | 1,191 MW |
| Wayne | 14 | 1,104 MW |
| Webster | 14 | 917 MW |
| Burt | 13 | 1,680 MW |
| Richardson | 13 | 247 MW |
| Nemaha | 12 | 2,144 MW |
| Johnson | 11 | 749 MW |
| Sarpy County | 11 | 1,583 MW |
| Platte | 11 | 138 MW |
| Saline | 11 | 803 MW |
| Dodge | 11 | 328 MW |
| Gage | 10 | 1,902 MW |
| Holt | 10 | 1,944 MW |
| Plattsmouth | 9 | 1,729 MW |
| Antelope | 9 | 1,831 MW |
| Scotts Bluff | 9 | 1,074 MW |
| Butler | 9 | 385 MW |
| Dixon | 9 | 644 MW |
| Antelope County | 9 | 791 MW |
| Cheyenne | 9 | 1,480 MW |
| Jefferson | 8 | 621 MW |
| Cedar | 8 | 756 MW |
| Thayer | 8 | 484 MW |
| Adams | 7 | 388 MW |
| Hall | 7 | 564 MW |
| Saunders | 7 | 95 MW |
| Franklin | 7 | 10 MW |
| Cuming | 7 | 11 MW |
| Greeley | 7 | 192 MW |
| Lancaster County | 6 | 1,548 MW |
| Kimball | 6 | 193 MW |
| Knox | 6 | 707 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| West Queue Project GI-2018-18 — Wind in Banner, Nebraska | GI-2018-18 | Wind | 1,000.0 MW | withdrawn | Banner, Nebraska |
| Cooper Nuclear Station | 8036_1 | Other | 801.0 MW | operational | Nemaha, Nebraska |
| Nebraska City | 6096_2 | Other | 738.0 MW | operational | Otoe, Nebraska |
| GEN-2003-008O | GEN-2003-008O | Other | 700.0 MW | operational | Otoe County, Nebraska |
| Gerald Gentleman | 6077_2 | Other | 681.3 MW | operational | Lincoln, Nebraska |
| Gerald Gentleman | 6077_1 | Other | 681.3 MW | operational | Lincoln, Nebraska |
| Nebraska City | 6096_1 | Other | 651.6 MW | operational | Otoe, Nebraska |
| GEN-2007-011N02 | GEN-2007-011N02 | Other | 600.0 MW | withdrawn | Lancaster County, Nebraska |
| West Queue Project GI-1405 — Wind in Banner, Nebraska | GI-1405 | Wind | 600.0 MW | withdrawn | Banner, Nebraska |
| 345kV bus of Turtle Creek Substation | GEN-2021-007 | Wind | 600.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Gentleman – Red Willow 345kV Line Break | GEN-2018-045 | Solar | 550.0 MW | withdrawn | Banner, Nebraska |
| Olive Creek 345 kV Substation | GEN-2024-021 | Gas | 540.0 MW | operational | Lancaster, Nebraska |
| West Queue Project GI-2018-16 — Wind in Banner, Nebraska | GI-2018-16 | Wind | 501.5 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-17 — Wind in Banner, Nebraska | GI-2018-17 | Wind | 501.5 MW | withdrawn | Banner, Nebraska |
| Fort Calhoun 345kV Substation | GEN-2018-044 | Solar | 500.0 MW | withdrawn | Antelope, Nebraska |
| Keystone 345 kV Substation | GEN-2023-116 | Wind | 500.0 MW | withdrawn | Keith, Deuel, Garden, Nebraska |
| Ft. Calhoun - Raun 345 kV Line Break | GEN-2018-043 | Solar | 500.0 MW | active | Burt, Nebraska |
| Stranger Creek 345kV substation | GEN-2018-110 | Wind | 500.0 MW | withdrawn | Nemaha, Nebraska |
| Gerald Gentleman-Red Willow 345kV transmssion line | GEN-2019-007 | Solar | 500.0 MW | withdrawn | Lincoln, Nebraska |
| Olive Creek 345 kV Substation | GEN-2023-224 | Other | 478.0 MW | active | Lancaster, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2023-222 | Other | 478.0 MW | active | Gage, Nebraska |
| Hoskins 345kV | GEN-2016-159 | Wind | 427.8 MW | withdrawn | Stanton, Nebraska |
| Substation 1363; 161kV Substation | GEN-2020-024 | Other | 424.5 MW | withdrawn | Sarpy County, Nebraska |
| Substation 3740; 345kV | GEN-2020-035 | Other | 424.5 MW | withdrawn | Plattsmouth, Nebraska |
| Sidney Keystone 345 kV line | GEN-2019-029 | Wind | 404.0 MW | withdrawn | Keith And Deuel, Nebraska |
| West Queue Project GI-2018-10 — Wind in Banner, Nebraska | GI-2018-10 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-12 — Wind in Banner, Nebraska | GI-2018-12 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-8 — Wind in Banner, Nebraska | GI-2018-8 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-7 — Wind in Banner, Nebraska | GI-2018-7 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| GEN-2008-121N01 | GEN-2008-121N01 | Wind | 400.0 MW | withdrawn | Saline County, Nebraska |
Top developers in Nebraska
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Grande Prairie Wind | 2 | 400 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-24 | Monolith 115kV | proposed_online_date | 2027-04-01 | 2026-12-01 |
| 2026-11-24 | Monolith 115kV | proposed_online_date | 2027-04-01 | 2026-12-01 |
| 2026-11-19 | Monolith 115kV | proposed_online_date | 2026-12-01 | 2027-04-01 |
| 2026-11-19 | Monolith 115kV | proposed_online_date | 2026-12-01 | 2027-04-01 |
| 2026-11-19 | 115kV Monolith Substation | proposed_online_date | 2028-12-31 | 2027-04-01 |
| 2026-11-01 | Burt County Wind | proposed_online_date | 2027-07-01 | 2029-09-01 |
| 2026-11-01 | Burt County Solar (Sandhills Energy) | new_project | — | active |
| 2026-10-06 | Hoskins 345 kV Substation | proposed_online_date | 2024-12-31 | 2027-11-01 |
| 2026-10-03 | Fort Calhoun 345kV Substation | proposed_online_date | 2028-11-30 | 2030-10-01 |
| 2026-10-03 | Cass County 345kV Substation | proposed_online_date | 2029-11-30 | 2031-08-31 |
| 2026-10-03 | Looping in OPPD (S1211) (S1220) (S1211) (S1299) 161kV | proposed_online_date | 2030-05-31 | 2032-05-31 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: cheyenne-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue; wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in Nebraska.