Nebraska Interconnection Projects
interXdata tracks 743 interconnection projects in Nebraska representing 84,105 MW of requested capacity. The dominant technology by capacity is Wind. The most active counties are Lancaster, Douglas, Lincoln.
743Total projects
88Active
366Operational
282Withdrawn
84,105 MWRequested capacity
13,133 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 250 | 38,932 MW |
| Solar | 113 | 16,299 MW |
| Other | 177 | 13,937 MW |
| Gas | 160 | 10,031 MW |
| Battery | 41 | 4,526 MW |
| Solar+Battery | 2 | 380 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Lancaster | 58 | 5,645 MW |
| Douglas | 24 | 1,789 MW |
| Lincoln | 20 | 4,671 MW |
| Custer | 19 | 1,390 MW |
| Banner | 18 | 7,196 MW |
| Cass | 17 | 3,669 MW |
| Otoe | 16 | 1,734 MW |
| Sarpy | 15 | 1,139 MW |
| Madison | 15 | 1,191 MW |
| Wayne | 14 | 1,104 MW |
| Webster | 14 | 917 MW |
| Richardson | 13 | 247 MW |
| Nemaha | 12 | 2,144 MW |
| Burt | 12 | 1,430 MW |
| Dodge | 11 | 328 MW |
| Sarpy County | 11 | 1,583 MW |
| Saline | 11 | 803 MW |
| Platte | 11 | 139 MW |
| Johnson | 11 | 749 MW |
| Gage | 10 | 1,902 MW |
| Holt | 10 | 1,944 MW |
| Antelope County | 9 | 791 MW |
| Butler | 9 | 385 MW |
| Scotts Bluff | 9 | 1,074 MW |
| Plattsmouth | 9 | 1,729 MW |
| Cheyenne | 9 | 1,480 MW |
| Antelope | 9 | 1,831 MW |
| Dixon | 9 | 644 MW |
| Cedar | 8 | 756 MW |
| Jefferson | 8 | 621 MW |
| Thayer | 8 | 484 MW |
| Saunders | 7 | 95 MW |
| Cuming | 7 | 11 MW |
| Hall | 7 | 564 MW |
| Adams | 7 | 388 MW |
| Greeley | 7 | 192 MW |
| Franklin | 7 | 10 MW |
| Furnas | 6 | 7 MW |
| Custer County | 6 | 530 MW |
| Washington | 6 | 580 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| West Queue Project GI-2018-18 — Wind in Banner, Nebraska | GI-2018-18 | Wind | 1,000.0 MW | withdrawn | Banner, Nebraska |
| Cooper Nuclear Station | 8036_1 | Other | 801.0 MW | operational | Nemaha, Nebraska |
| Nebraska City | 6096_2 | Other | 738.0 MW | operational | Otoe, Nebraska |
| GEN-2003-008O | GEN-2003-008O | Other | 700.0 MW | operational | Otoe County, Nebraska |
| Gerald Gentleman | 6077_2 | Other | 681.3 MW | operational | Lincoln, Nebraska |
| Gerald Gentleman | 6077_1 | Other | 681.3 MW | operational | Lincoln, Nebraska |
| Nebraska City | 6096_1 | Other | 651.6 MW | operational | Otoe, Nebraska |
| West Queue Project GI-1405 — Wind in Banner, Nebraska | GI-1405 | Wind | 600.0 MW | withdrawn | Banner, Nebraska |
| GEN-2007-011N02 | GEN-2007-011N02 | Other | 600.0 MW | withdrawn | Lancaster County, Nebraska |
| 345kV bus of Turtle Creek Substation | GEN-2021-007 | Wind | 600.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Gentleman – Red Willow 345kV Line Break | GEN-2018-045 | Solar | 550.0 MW | withdrawn | Banner, Nebraska |
| Olive Creek 345 kV Substation | GEN-2024-021 | Gas | 540.0 MW | operational | Lancaster, Nebraska |
| West Queue Project GI-2018-16 — Wind in Banner, Nebraska | GI-2018-16 | Wind | 501.5 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-17 — Wind in Banner, Nebraska | GI-2018-17 | Wind | 501.5 MW | withdrawn | Banner, Nebraska |
| Keystone 345 kV Substation | GEN-2023-116 | Wind | 500.0 MW | withdrawn | Keith, Deuel, Garden, Nebraska |
| Stranger Creek 345kV substation | GEN-2018-110 | Wind | 500.0 MW | withdrawn | Nemaha, Nebraska |
| Fort Calhoun 345kV Substation | GEN-2018-044 | Solar | 500.0 MW | withdrawn | Antelope, Nebraska |
| Gerald Gentleman-Red Willow 345kV transmssion line | GEN-2019-007 | Solar | 500.0 MW | withdrawn | Lincoln, Nebraska |
| Ft. Calhoun - Raun 345 kV Line Break | GEN-2018-043 | Solar | 500.0 MW | active | Burt, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2023-222 | Other | 478.0 MW | active | Gage, Nebraska |
| Olive Creek 345 kV Substation | GEN-2023-224 | Other | 478.0 MW | active | Lancaster, Nebraska |
| Hoskins 345kV | GEN-2016-159 | Wind | 427.8 MW | withdrawn | Stanton, Nebraska |
| Substation 3740; 345kV | GEN-2020-035 | Other | 424.5 MW | withdrawn | Plattsmouth, Nebraska |
| Substation 1363; 161kV Substation | GEN-2020-024 | Other | 424.5 MW | withdrawn | Sarpy County, Nebraska |
| Sidney Keystone 345 kV line | GEN-2019-029 | Wind | 404.0 MW | withdrawn | Keith And Deuel, Nebraska |
| West Queue Project GI-2018-10 — Wind in Banner, Nebraska | GI-2018-10 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-8 — Wind in Banner, Nebraska | GI-2018-8 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-7 — Wind in Banner, Nebraska | GI-2018-7 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| West Queue Project GI-2018-12 — Wind in Banner, Nebraska | GI-2018-12 | Wind | 400.7 MW | withdrawn | Banner, Nebraska |
| Gerald Gentleman 345kV switchyard | GEN-2018-066 | Solar | 400.0 MW | withdrawn | Lincoln, Nebraska |
Top developers in Nebraska
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Grande Prairie Wind | 2 | 400 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-06 | Hoskins 345 kV Substation | proposed_online_date | 2024-12-31 | 2027-11-01 |
| 2026-10-03 | Fort Calhoun 345kV Substation | proposed_online_date | 2028-11-30 | 2030-10-01 |
| 2026-10-03 | Cass County 345kV Substation | proposed_online_date | 2029-11-30 | 2031-08-31 |
| 2026-10-03 | Looping in OPPD (S1211) (S1220) (S1211) (S1299) 161kV | proposed_online_date | 2030-05-31 | 2032-05-31 |
| 2026-09-20 | Antelope - Hoskins 345 kV | proposed_online_date | 2026-12-31 | 2031-12-01 |
| 2026-09-15 | Archer - Stegall 230kV | status | active | withdrawn |
| 2026-09-02 | VS Hemingford NE Solar LLC | new_project | — | operational |
| 2026-09-02 | 2nd & N BESS | operational_date | — | 2026-07-01 |
| 2026-09-02 | 2nd & N BESS | proposed_online_date | 2026-07-01 | — |
| 2026-09-02 | 2nd & N BESS | status | active | operational |
| 2026-09-02 | Haystack Wind Project, LLC | operational_date | 2022-03-01 | 2022-02-01 |
| 2026-09-02 | Steele Flats Energy Storage | new_project | — | active |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: cheyenne-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue; wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in Nebraska.