Lawrenceburg 345kV PB I (AC1-152)

Lawrenceburg 345kV PB I is a 50.0 MW gas interconnection project in Dearborn, Indiana with a current status of operational.

50.0 MWCapacity
OperationalStatus
—Market
GasTechnology

Project facts

Canonical nameLawrenceburg 345kV PB I
Queue IDAC1-152
Statusoperational
Source statusIn Service
Market—
TechnologyGas
Capacity50.0 MW
StateIndiana
CountyDearborn
Point of interconnection—
Requested (queue) date2016-10-31
Proposed in-service date—
Operational date2020-06-01
Withdrawn date—
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.