Lawton East Side-Sunnyside (Terry Road) 345kV (GEN-2015-045)

Lawton East Side-Sunnyside (Terry Road) 345kV is a 10.3 MW battery interconnection project in Grady County, Oklahoma with a current status of operational. It is proposed to connect at Lawton East Side-Sunnyside (Terry Road) 345kV.

10.3 MWCapacity
OperationalStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameLawton East Side-Sunnyside (Terry Road) 345kV
Queue IDGEN-2015-045
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologyBattery
Capacity10.3 MW
StateOklahoma
CountyGrady County
Point of interconnectionLawton East Side-Sunnyside (Terry Road) 345kV
Requested (queue) date2015-10-05
Proposed in-service date
Operational date2017-12-01
Withdrawn date
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata