Lazy U Solar 2 is a 252.0 MW solar interconnection project in Hardeman, Texas with a current status of operational. It is proposed to connect at Tap 345kV 60505 EDITHCLA7B - 60501 TESLA7A CKT2.

252.0 MWCapacity
OperationalStatus
HardemanMarket
SolarTechnology

Project facts

Canonical nameLazy U Solar 2
Queue ID26INR0172
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketHardeman
TechnologySolar
Capacity252.0 MW
StateTexas
CountyHardeman
Point of interconnectionTap 345kV 60505 EDITHCLA7B - 60501 TESLA7A CKT2
Requested (queue) date2023-08-21
Proposed in-service date
Operational date2029-06-30
Withdrawn date
DeveloperLazy U Solar 2
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata