Leighton Solar (24INR0298)

Leighton Solar is a 181.0 MW solar interconnection project in Limestone, Texas with a current status of operational. It is proposed to connect at 98 Fernleaf 138 kV.

181.0 MWCapacity
OperationalStatus
LimestoneMarket
SolarTechnology

Project facts

Canonical nameLeighton Solar
Queue ID24INR0298
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketLimestone
TechnologySolar
Capacity181.0 MW
StateTexas
CountyLimestone
Point of interconnection98 Fernleaf 138 kV
Requested (queue) date2022-05-11
Proposed in-service date—
Operational date2027-12-06
Withdrawn date—
DeveloperLavender Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31poi_nameFernleaf 138 kV98 Fernleaf 138 kVlow
2026-08-31operational_date2027-11-012027-12-06medium
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata