Lemoyne 345kV (AH1-565 - moved to TC2)

Lemoyne 345kV is a 250.0 MW battery interconnection project in Wood, Ohio with a current status of withdrawn.

250.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameLemoyne 345kV
Queue IDAH1-565 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity250.0 MW
StateOhio
CountyWood
Point of interconnection
Requested (queue) date2021-09-10
Proposed in-service date2025-06-01
Operational date
Withdrawn date2025-05-07
Developer
Utility / transmission ownerATSI

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata