Lena - Lancaster 138 kV (AF1-314 - moved to TC1)

Lena - Lancaster 138 kV is a 212.0 MW wind interconnection project in Stephenson, Illinois with a current status of withdrawn.

212.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameLena - Lancaster 138 kV
Queue IDAF1-314 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity212.0 MW
StateIllinois
CountyStephenson
Point of interconnection
Requested (queue) date2019-09-30
Proposed in-service date2022-09-15
Operational date
Withdrawn date2025-01-22
Developer
Utility / transmission ownerComEd

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.