Leon Solar Park (26INR0023)

Leon Solar Park is a 210.1 MW solar interconnection project in Leon, Texas with a current status of operational. It is proposed to connect at Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line.

210.1 MWCapacity
OperationalStatus
LeonMarket
SolarTechnology

Project facts

Canonical nameLeon Solar Park
Queue ID26INR0023
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketLeon
TechnologySolar
Capacity210.1 MW
StateTexas
CountyLeon
Point of interconnectionTap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line
Requested (queue) date2022-09-15
Proposed in-service date
Operational date2026-07-01
Withdrawn date
DeveloperMisae Solar IV LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.