Longfellow Solar II (24INR0454)

Longfellow Solar II is a 207.4 MW solar interconnection project in Pecos, Texas with a current status of operational. It is proposed to connect at 38432 TNCENTRY2_1 138 KV .

207.4 MWCapacity
OperationalStatus
PecosMarket
SolarTechnology

Project facts

Canonical nameLongfellow Solar II
Queue ID24INR0454
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketPecos
TechnologySolar
Capacity207.4 MW
StateTexas
CountyPecos
Point of interconnection38432 TNCENTRY2_1 138 KV
Requested (queue) date2022-11-07
Proposed in-service date
Operational date2028-12-31
Withdrawn date
DeveloperCENTURY GAS PROCESSING, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.