LOS MEDANOS ENERGY CENTER (963)

LOS MEDANOS ENERGY CENTER is a 72.0 MW gas interconnection project in Contra Costa, California with a current status of operational. It is proposed to connect at Pittsburg Substation 115 kV bus.

72.0 MWCapacity
OperationalStatus
NoneMarket
GasTechnology

Project facts

Canonical nameLOS MEDANOS ENERGY CENTER
Queue ID963
Statusoperational
Source statusCOMPLETED
MarketNone
TechnologyGas
Capacity72.0 MW
StateCalifornia
CountyContra Costa
Point of interconnectionPittsburg Substation 115 kV bus
Requested (queue) date2013-04-30
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata