Lower Rio BESS (22INR0468)

Lower Rio BESS is a 60.4 MW battery interconnection project with a current status of operational. It is proposed to connect at 5792 Sioux 138kV.

60.4 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameLower Rio BESS
Queue ID22INR0468
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity60.4 MW
State
County
Point of interconnection5792 Sioux 138kV
Requested (queue) date2021-02-09
Proposed in-service date2025-08-11
Operational date2025-08-12
Withdrawn date
DeveloperVESI 37 LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata