Lumberton 69kV (W3-055)

Lumberton 69kV is a 12.0 MW solar interconnection project in Burlington, New Jersey with a current status of withdrawn.

12.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameLumberton 69kV
Queue IDW3-055
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity12.0 MW
StateNew Jersey
CountyBurlington
Point of interconnection—
Requested (queue) date2010-09-01
Proposed in-service date2011-11-30
Operational date—
Withdrawn date2011-09-07
Developer—
Utility / transmission ownerPSEG Long Island

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata