interXdata tracks 2,003 interconnection projects in New Jersey representing 149,042 MW of requested capacity. The dominant technology by capacity is Gas. The most active counties are Middlesex, Burlington, Warren.

2,003Total projects
52Active
885Operational
1,054Withdrawn
149,042 MWRequested capacity
3,221 MWActive capacity

Technology mix

TechnologyProjectsRequested capacity
Gas46475,957 MW
Wind6438,325 MW
Other11112,594 MW
Battery16711,394 MW
Solar1,1949,182 MW
Offshore Wind11,300 MW
Nuclear1257 MW
Solar+Battery133 MW

Counties

CountyProjectsRequested capacity
Middlesex21736,325 MW
Burlington1604,201 MW
Warren1452,437 MW
Salem1229,768 MW
Cumberland1202,889 MW
Gloucester1198,071 MW
Atlantic11912,141 MW
Hunterdon1093,410 MW
Monmouth10720,299 MW
Union8910,118 MW
Ocean896,928 MW
Hudson8711,076 MW
Camden803,128 MW
Sussex771,833 MW
Bergen644,767 MW
Essex634,289 MW
Mercer621,055 MW
Morris41312 MW
Somerset401,862 MW
Cape May372,418 MW
Passaic2947 MW
Unknown143 MW
N/a33 MW
Bayonne2750 MW
Various152 MW
Yates118 MW
Hudson County1600 MW
Linden1208 MW

Largest projects

ProjectQueue IDTechnologyCapacityStatusLocation
Larrabee Collector Station 230 kVAI2-431Wind2,138.8 MWwithdrawnAtlantic, New Jersey
Larrabee 230 kVAI1-001Wind2,100.0 MWwithdrawnMonmouth, New Jersey
Smithburg 500 kVAI1-046Wind1,600.0 MWwithdrawnMonmouth, New Jersey
PJM Queue Project AH2-196 — Wind in Monmouth, New JerseyAH2-196Wind1,600.0 MWwithdrawnMonmouth, New Jersey
Oceanview 230 kVAH2-240Wind1,493.0 MWwithdrawnMonmouth, New Jersey
PJM Queue Project AH2-285 — Wind in Middlesex, New JerseyAH2-285Wind1,400.0 MWwithdrawnMiddlesex, New Jersey
PJM Queue Project AH2-286 — Wind in Middlesex, New JerseyAH2-286Wind1,400.0 MWwithdrawnMiddlesex, New Jersey
Branchburg-Deans 500kVAA2-142Gas1,377.0 MWwithdrawnSomerset, New Jersey
Larrabee Collector 230 kVAJ1-015Wind1,342.0 MWwithdrawnMonmouth, New Jersey
South AmboyU2-098Gas1,320.0 MWwithdrawnMiddlesex, New Jersey
Larrabee 230 kV VAI1-110Wind1,310.0 MWwithdrawnMonmouth, New Jersey
Deans 500 kVAI1-109Wind1,310.0 MWwithdrawnMiddlesex, New Jersey
Werner 230 kVAI1-111Wind1,310.0 MWwithdrawnMiddlesex, New Jersey
Larrabee 230 kV IVAH1-557Offshore Wind1,300.0 MWwithdrawnMonmouth, New Jersey
Deans 500 kVAG2-055Wind1,300.0 MWwithdrawnMiddlesex, New Jersey
Larrabee Collector Station 230 kVAH1-557 - moved to TC2Wind1,300.0 MWwithdrawnMonmouth, New Jersey
PSEG Hope Creek Generating Station6118_1Other1,290.7 MWoperationalSalem, New Jersey
Werner 230 kV-Ravenwood 345 kVAG2-146Other1,242.0 MWwithdrawnMiddlesex, New Jersey
Liberty BESSC24-119Battery1,200.0 MWwithdrawnHudson, New Jersey
Cardiff 230 kVAE2-251Wind1,200.0 MWwithdrawnMonmouth, New Jersey
Deans 500kVAE1-037Wind1,200.0 MWwithdrawnMiddlesex, New Jersey
Sewaren 230 kVAE2-014Wind1,200.0 MWwithdrawnMiddlesex, New Jersey
PSEG Salem Generating Station2410_1Other1,170.0 MWoperationalSalem, New Jersey
PSEG Salem Generating Station2410_2Other1,170.0 MWoperationalSalem, New Jersey
Larrabee 230 kVAE1-034Wind1,104.0 MWwithdrawnAtlantic, New Jersey
Gilbert 230kVAB1-154Gas1,092.2 MWwithdrawnHunterdon, New Jersey
Bayonne 345kVAB2-055Gas1,041.4 MWwithdrawnHudson, New Jersey
Branchburg-Deans 500kVU2-006Gas1,010.0 MWwithdrawnMiddlesex, New Jersey
Branchburg-Deans 500kVU2-005Gas1,010.0 MWwithdrawnMiddlesex, New Jersey
Bergen 230kVQ75Other1,000.0 MWwithdrawnBergen, New Jersey

Top developers in New Jersey

Recent material changes

ObservedProjectFieldOldNew
2026-10-07Mercer 230 kVproposed_online_date2027-08-112028-08-11
2026-10-02Milltown Onsite BESSproposed_online_date2026-08-012026-10-01
2026-10-0250 Meister Aveproposed_online_date2026-09-012026-10-01
2026-10-02BPL NJ - Union Distribution Centerproposed_online_date2026-08-012026-09-01
2026-10-02Esky Solaroperational_date—2026-08-01
2026-10-02Esky Solarproposed_online_date2026-08-01—
2026-10-02Esky Solarstatusactiveoperational
2026-10-01Oyster Creek-Whitings 34.5 kVproposed_online_date—2027-09-01
2026-10-01Linden 230kVproposed_online_date—2030-05-31
2026-10-01Linden 138kV & 230kVproposed_online_date—2029-05-31
2026-10-01Salem 500kVproposed_online_date—2027-10-22
2026-10-01Bergen 230kVproposed_online_date—2027-05-21

Explore related data

Source last checked2026-07-31
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; New York ISO — interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get notified when a new project appears in New Jersey.

Start tracking with interXdata