Lupinus Storage 1 (24INR0153)

Lupinus Storage 1 is a 84.0 MW other interconnection project in Franklin, Texas with a current status of operational. It is proposed to connect at Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES .

84.0 MWCapacity
OperationalStatus
FranklinMarket
OtherTechnology

Project facts

Canonical nameLupinus Storage 1
Queue ID24INR0153
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketFranklin
TechnologyOther
Capacity84.0 MW
StateTexas
CountyFranklin
Point of interconnectionTap 345 kV 11699 Woodard Switch - 1695 Monticello SES
Requested (queue) date2021-12-13
Proposed in-service date
Operational date2027-09-13
Withdrawn date
DeveloperLupinus BESS 2, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata