Luyster Creek Energy Storage 1 (0835)

Luyster Creek Energy Storage 1 is a 56.3 MW battery interconnection project in Queens, New York with a current status of active. It is proposed to connect at Astoria West 138kV.

56.3 MWCapacity
ActiveStatus
JMarket
BatteryTechnology

Project facts

Canonical nameLuyster Creek Energy Storage 1
Queue ID0835
Statusactive
Source status11
MarketJ
TechnologyBattery
Capacity56.3 MW
StateNew York
CountyQueens
Point of interconnectionAstoria West 138kV
Requested (queue) date2019-05-07
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperEastern Generation, LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.