Luyster Creek Energy Storage 3 (0930)

Luyster Creek Energy Storage 3 is a 15.0 MW battery interconnection project in Queens, New York with a current status of withdrawn. It is proposed to connect at North Queens 27kV.

15.0 MWCapacity
WithdrawnStatus
JMarket
BatteryTechnology

Project facts

Canonical nameLuyster Creek Energy Storage 3
Queue ID0930
Statuswithdrawn
Source status0
MarketJ
TechnologyBattery
Capacity15.0 MW
StateNew York
CountyQueens
Point of interconnectionNorth Queens 27kV
Requested (queue) date2019-10-25
Proposed in-service date2026-10-31
Operational date—
Withdrawn date—
DeveloperEastern Generation, LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-13proposed_online_date—2026-10-31medium
2026-11-13statusactivewithdrawnhigh
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata