Lytton Springs BESS (27INR0585)
Lytton Springs BESS is a 76.4 MW other interconnection project in Caldwell, Texas with a current status of operational. It is proposed to connect at Lytton Springs (#9074) – Fayette Plant (#7055) 345 kV Line.
76.4 MWCapacity
OperationalStatus
CaldwellMarket
OtherTechnology
Project facts
| Canonical name | Lytton Springs BESS |
|---|---|
| Queue ID | 27INR0585 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Caldwell |
| Technology | Other |
| Capacity | 76.4 MW |
| State | Texas |
| County | Caldwell |
| Point of interconnection | Lytton Springs (#9074) – Fayette Plant (#7055) 345 kV Line |
| Requested (queue) date | 2025-12-02 |
| Proposed in-service date | — |
| Operational date | 2029-12-01 |
| Withdrawn date | — |
| Developer | SMT Lytton Springs LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.