Macho Creek BESS (25INR0390)

Macho Creek BESS is a 150.6 MW battery interconnection project in Starr, Texas with a current status of withdrawn.

150.6 MWCapacity
WithdrawnStatus
StarrMarket
BatteryTechnology

Project facts

Canonical nameMacho Creek BESS
Queue ID25INR0390
Statuswithdrawn
Source status—
MarketStarr
TechnologyBattery
Capacity150.6 MW
StateTexas
CountyStarr
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date—
Withdrawn date2026-07-16
Developer—
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31developerMacho Creek BESS, LLC—low
2026-08-31poi_nameTap 138kV 8793 RIO GRANDE CITY - 8806 LAS LOMAS—low
2026-08-31phaseSS Completed, FIS Started, No IA—low
2026-08-31operational_date2027-05-31—medium
2026-08-31withdrawn_date—2026-07-16high
2026-08-31statusoperationalwithdrawnhigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-08-31
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.