Mahomet - Weedman 138 kV Line Tap (J1118)

Mahomet - Weedman 138 kV Line Tap is a 150.0 MW wind interconnection project in Piatt County, Illinois with a current status of withdrawn. It is proposed to connect at Mahomet - Weedman 138 kV Line Tap.

150.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameMahomet - Weedman 138 kV Line Tap
Queue IDJ1118
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity150.0 MW
StateIllinois
CountyPiatt County
Point of interconnectionMahomet - Weedman 138 kV Line Tap
Requested (queue) date2018-03-12
Proposed in-service date2021-09-01
Operational date2021-09-01
Withdrawn date2018-10-03
Developer
Utility / transmission ownerAMEREN ILLINOIS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.