MAIZEN BLUE SOLAR 1 (1237)

MAIZEN BLUE SOLAR 1 is a 80.8 MW solar+battery interconnection project in Fresno, California with a current status of withdrawn. It is proposed to connect at Excelsior Switching Station located on the Panoche-Schindler No.1 & 2 115 kV line.

80.8 MWCapacity
WithdrawnStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameMAIZEN BLUE SOLAR 1
Queue ID1237
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar+Battery
Capacity80.8 MW
StateCalifornia
CountyFresno
Point of interconnectionExcelsior Switching Station located on the Panoche-Schindler No.1 & 2 115 kV line
Requested (queue) date2016-05-02
Proposed in-service date
Operational date
Withdrawn date2017-05-04
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata