Marcy BESS is a 199.9 MW battery interconnection project in Oneida, New York with a current status of active. It is proposed to connect at Marcy T1 345 kV.
199.9 MWCapacity
ActiveStatus
EMarket
BatteryTechnology
Project facts
| Canonical name | Marcy BESS |
|---|---|
| Queue ID | C26-0038 |
| Status | active |
| Source status | 2 |
| Market | E |
| Technology | Battery |
| Capacity | 199.9 MW |
| State | New York |
| County | Oneida |
| Point of interconnection | Marcy T1 345 kV |
| Requested (queue) date | 2026-08-27 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | RWE Solar Development, LLC |
| Utility / transmission owner | NYPA |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-10-14 | new_project | — | active | high |
Explore related data
Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata