Marion - Marked Tree 161kV Line Tap (J1007)

Marion - Marked Tree 161kV Line Tap is a 200.0 MW solar interconnection project in Crittenden County, Arkansas with a current status of operational. It is proposed to connect at Marion - Marked Tree 161kV Line Tap.

200.0 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical nameMarion - Marked Tree 161kV Line Tap
Queue IDJ1007
Statusoperational
Source statusDone
Market
TechnologySolar
Capacity200.0 MW
StateArkansas
CountyCrittenden County
Point of interconnectionMarion - Marked Tree 161kV Line Tap
Requested (queue) date2018-03-12
Proposed in-service date2021-09-01
Operational date2021-09-01
Withdrawn date
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata