Martin 115 kV Substation (GEN-2026-SR14)

Martin 115 kV Substation is a 158.0 MW battery interconnection project in Panhandle, Texas with a current status of active. It is proposed to connect at Martin 115 kV Substation.

158.0 MWCapacity
ActiveStatus
TXMarket
BatteryTechnology

Project facts

Canonical nameMartin 115 kV Substation
Queue IDGEN-2026-SR14
Statusactive
Source statusSPECIAL STUDY
MarketTX
TechnologyBattery
Capacity158.0 MW
StateTexas
CountyPanhandle
Point of interconnectionMartin 115 kV Substation
Requested (queue) date2026-01-16
Proposed in-service date2028-12-29
Operational date
Withdrawn date
Developer
Utility / transmission ownerSPS

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata