Martin 115kV (GEN-2003-020)

Martin 115kV is a 159.1 MW wind interconnection project in Carson County, Texas with a current status of operational. It is proposed to connect at Martin 115kV.

159.1 MWCapacity
OperationalStatus
TXMarket
WindTechnology

Project facts

Canonical nameMartin 115kV
Queue IDGEN-2003-020
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketTX
TechnologyWind
Capacity159.1 MW
StateTexas
CountyCarson County
Point of interconnectionMartin 115kV
Requested (queue) date2003-12-29
Proposed in-service date
Operational date2007-06-01
Withdrawn date
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata