Marysville-Tangy 345 kV (AG2-110)

Marysville-Tangy 345 kV is a 50.0 MW battery interconnection project in Union, Ohio with a current status of withdrawn.

50.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameMarysville-Tangy 345 kV
Queue IDAG2-110
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity50.0 MW
StateOhio
CountyUnion
Point of interconnection
Requested (queue) date2021-01-29
Proposed in-service date2024-06-01
Operational date
Withdrawn date2024-12-17
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata