MASSPOWER CNR Recovery (467)

MASSPOWER CNR Recovery is a 256.1 MW gas interconnection project in Hampden, Massachusetts with a current status of operational. It is proposed to connect at 115kV Shawinigan Substation.

256.1 MWCapacity
OperationalStatus
WMAMarket
GasTechnology

Project facts

Canonical nameMASSPOWER CNR Recovery
Queue ID467
Statusoperational
Source statusC
MarketWMA
TechnologyGas
Capacity256.1 MW
StateMassachusetts
CountyHampden
Point of interconnection115kV Shawinigan Substation
Requested (queue) date2014-05-29
Proposed in-service date
Operational date2014-11-10
Withdrawn date
Developer
Utility / transmission ownerISO-NE

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.