MATEP (Combined Cycle) Increase (433)

MATEP (Combined Cycle) Increase is a 1.7 MW gas interconnection project in Suffolk, Massachusetts with a current status of operational. It is proposed to connect at At existing point of interconnection for MATEP (Combined Cycle).

1.7 MWCapacity
OperationalStatus
BOSTMarket
GasTechnology

Project facts

Canonical nameMATEP (Combined Cycle) Increase
Queue ID433
Statusoperational
Source statusC
MarketBOST
TechnologyGas
Capacity1.7 MW
StateMassachusetts
CountySuffolk
Point of interconnectionAt existing point of interconnection for MATEP (Combined Cycle)
Requested (queue) date2014-01-24
Proposed in-service date
Operational date2014-04-21
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.