Mayfield Solar and Storage (68368_MYSO)

Mayfield Solar and Storage is a 200.0 MW solar interconnection project in McCracken, Kentucky with a current status of active.

200.0 MWCapacity
ActiveStatus
MISOMarket
SolarTechnology

Project facts

Canonical nameMayfield Solar and Storage
Queue ID68368_MYSO
Statusactive
Source status(L) Regulatory approvals pending. Not under construction
MarketMISO
TechnologySolar
Capacity200.0 MW
StateKentucky
CountyMcCracken
Point of interconnection—
Requested (queue) date—
Proposed in-service date2029-10-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerBrightNight Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-02proposed_online_date2028-12-012029-10-01medium
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.