McAlpin 12kV (Y1-013)

McAlpin 12kV is a 4.8 MW gas interconnection project in Harrison, West Virginia with a current status of withdrawn.

4.8 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameMcAlpin 12kV
Queue IDY1-013
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyGas
Capacity4.8 MW
StateWest Virginia
CountyHarrison
Point of interconnection—
Requested (queue) date2012-02-23
Proposed in-service date2013-09-09
Operational date—
Withdrawn date2012-03-28
Developer—
Utility / transmission ownerAPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.