McCartney (7903_MGS4)

McCartney is a 48.9 MW gas interconnection project in Greene, Missouri with a current status of active.

48.9 MWCapacity
ActiveStatus
SWPPMarket
GasTechnology

Project facts

Canonical nameMcCartney
Queue ID7903_MGS4
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketSWPP
TechnologyGas
Capacity48.9 MW
StateMissouri
CountyGreene
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-01-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerCity Utilities of Springfield - (MO)

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-11

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata