Melmore Tap 138kV (AD2-136)

Melmore Tap 138kV is a 360.0 MW wind interconnection project in Seneca, Ohio with a current status of withdrawn.

360.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameMelmore Tap 138kV
Queue IDAD2-136
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity360.0 MW
StateOhio
CountySeneca
Point of interconnection
Requested (queue) date2018-03-23
Proposed in-service date2021-10-31
Operational date
Withdrawn date2022-11-22
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.