Mercer 161kV is a 200.0 MW wind interconnection project in Henry, Illinois with a current status of operational. It is proposed to connect at Mercer 161kV.

200.0 MWCapacity
OperationalStatus
Market
WindTechnology

Project facts

Canonical nameMercer 161kV
Queue IDJ2614
Statusoperational
Source statusActive
Market
TechnologyWind
Capacity200.0 MW
StateIllinois
CountyHenry
Point of interconnectionMercer 161kV
Requested (queue) date2022-09-15
Proposed in-service date2028-09-30
Operational date2028-09-30
Withdrawn date
Developer
Utility / transmission ownerAMEREN ILLINOIS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.