Midway 345 kV II is a 150.0 MW solar interconnection project in Henry, Ohio with a current status of withdrawn.

150.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameMidway 345 kV II
Queue IDAG2-514
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity150.0 MW
StateOhio
CountyHenry
Point of interconnection
Requested (queue) date2021-03-31
Proposed in-service date2023-10-31
Operational date
Withdrawn date2024-12-13
Developer
Utility / transmission ownerATSI

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.