MIGUEL BESS (FKA MIGUEL) (1179)

MIGUEL BESS (FKA MIGUEL) is a 30.0 MW battery interconnection project in San Diego, California with a current status of withdrawn. It is proposed to connect at Miguel Substation 69kV bus.

30.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameMIGUEL BESS (FKA MIGUEL)
Queue ID1179
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyBattery
Capacity30.0 MW
StateCalifornia
CountySan Diego
Point of interconnectionMiguel Substation 69kV bus
Requested (queue) date2015-04-30
Proposed in-service date
Operational date
Withdrawn date2016-02-09
Developer
Utility / transmission ownerSDGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.