Milesburg-Moshannon 230 kV (AE2-128)

Milesburg-Moshannon 230 kV is a 20.0 MW solar interconnection project in Clearfield, Pennsylvania with a current status of withdrawn.

20.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameMilesburg-Moshannon 230 kV
Queue IDAE2-128
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity20.0 MW
StatePennsylvania
CountyClearfield
Point of interconnection
Requested (queue) date2019-02-28
Proposed in-service date2021-10-01
Operational date
Withdrawn date2019-04-12
Developer
Utility / transmission ownerPENELEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.