Milford Solar Phase II is a 310.0 MW solar interconnection project in Beaver, Utah with a current status of active.

310.0 MWCapacity
ActiveStatus
LDWPMarket
SolarTechnology

Project facts

Canonical nameMilford Solar Phase II
Queue ID69930_MS2
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketLDWP
TechnologySolar
Capacity310.0 MW
StateUtah
CountyBeaver
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-09-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerMilford Pepes Farm Road Solar LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.