Utah Interconnection Projects

interXdata tracks 1,195 interconnection projects in Utah representing 140,457 MW of requested capacity. The dominant technology by capacity is Solar+Battery. The most active counties are Utah, Iron, Salt Lake.

1,195Total projects
151Active
347Operational
679Withdrawn
140,457 MWRequested capacity
30,076 MWActive capacity

Technology mix

TechnologyProjectsRequested capacity
Solar+Battery26350,679 MW
Battery14426,415 MW
Solar35922,973 MW
Gas18022,653 MW
Wind759,297 MW
Other1246,912 MW
Geothermal23689 MW
Coal6345 MW
Hydro19269 MW
Other Storage1220 MW
Wind+Battery14 MW

Counties

CountyProjectsRequested capacity
Utah14425,418 MW
Iron13314,418 MW
Salt Lake13211,616 MW
Beaver1126,551 MW
Millard9817,467 MW
Emery9016,026 MW
Box Elder746,839 MW
Tooele717,161 MW
Juab6112,693 MW
Washington592,384 MW
San Juan476,870 MW
Weber242,020 MW
Cache19470 MW
Wasatch1750 MW
Carbon171,969 MW
Sanpete151,381 MW
Sevier141,776 MW
Davis11193 MW
Rich111,131 MW
Summit10416 MW
Duchesne10721 MW
Kane81,764 MW
Garfield56 MW
Uintah3532 MW
Daggett3152 MW
Morgan24 MW
Tremonton13 MW
Carbon/Utah1100 MW
Miller175 MW
Grand10 MW
Kane County1250 MW

Largest projects

ProjectQueue IDTechnologyCapacityStatusLocation
PACE Queue Project IS008 — Solar+Battery in Iron, UtahIS008Solar+Battery1,000.0 MWoperationalIron, Utah
West Queue Project Q93 — Solar+Battery in Millard, UtahQ93Solar+Battery1,000.0 MWactiveMillard, Utah
PACE Queue Project IS018 — Other in Tooele, UtahIS018Other1,000.0 MWoperationalTooele, Utah
West Queue Project 28 — Gas in Utah, Utah28Gas890.0 MWwithdrawnUtah, Utah
Intermountain Power Project6481_2Other820.0 MWoperationalMillard, Utah
West Queue Project 301 — Gas in Utah, Utah301Gas712.0 MWoperationalUtah, Utah
West Queue Project 1167 — Battery in Box Elder, Utah1167Battery650.0 MWwithdrawnBox Elder, Utah
West Queue Project 240 — Gas in Utah, Utah240Gas636.3 MWwithdrawnUtah, Utah
West Queue Project 227 — Gas in Utah, Utah227Gas625.0 MWwithdrawnUtah, Utah
West Queue Project 207 — Gas in Utah, Utah207Gas625.0 MWwithdrawnUtah, Utah
PACE Queue Project C4-033 — Wind in Millard, UtahC4-033Wind600.0 MWwithdrawnMillard, Utah
West Queue Project Q105 — Solar+Battery in Millard, UtahQ105Solar+Battery600.0 MWactiveMillard, Utah
PACE Queue Project T2-092 — Wind in Millard, UtahT2-092Wind600.0 MWwithdrawnMillard, Utah
West Queue Project 986 — Solar in Beaver, Utah986Solar600.0 MWwithdrawnBeaver, Utah
West Queue Project 44 — Gas in Utah, Utah44Gas567.0 MWoperationalUtah, Utah
West Queue Project 43 — Gas in Utah, Utah43Gas567.0 MWwithdrawnUtah, Utah
West Queue Project 15 — Gas in Juab, Utah15Gas550.0 MWwithdrawnJuab, Utah
PACE Queue Project C4-082 — Gas in Juab, UtahC4-082Gas550.0 MWwithdrawnJuab, Utah
Intermountain Power Project6481_3Gas546.6 MWoperationalMillard, Utah
Intermountain Power Project6481_4Gas546.6 MWoperationalMillard, Utah
West Queue Project TCS-01 — Solar+Battery in Utah, UtahTCS-01Solar+Battery525.0 MWwithdrawnUtah, Utah
PACE Queue Project C4-083 — Gas in San Juan, UtahC4-083Gas525.0 MWwithdrawnSan Juan, Utah
West Queue Project 976 — Solar+Battery in Utah, Utah976Solar+Battery525.0 MWwithdrawnUtah, Utah
West Queue Project 22 — Gas in Juab, Utah22Gas525.0 MWwithdrawnJuab, Utah
West Queue Project 771 — Solar in Iron, Utah771Solar525.0 MWwithdrawnIron, Utah
West Queue Project 978 — Solar+Battery in Box Elder, Utah978Solar+Battery525.0 MWwithdrawnBox Elder, Utah
West Queue Project 403 — Gas in Sevier, Utah403Gas525.0 MWwithdrawnSevier, Utah
West Queue Project 838 — Solar+Battery in Utah, Utah838Solar+Battery525.0 MWactiveUtah, Utah
Faraday Solar69748_FARPVSolar525.0 MWoperationalUtah, Utah
West Queue Project 839 — Solar+Battery in Utah, Utah839Solar+Battery525.0 MWwithdrawnUtah, Utah

Top developers in Utah

Recent material changes

ObservedProjectFieldOldNew
2026-11-16PACE Queue Project FT050 — Battery in Salt Lake, Utahnew_project—active
2026-11-16PACE Queue Project FT048 — Battery in Salt Lake, Utahnew_project—active
2026-11-16PACE Queue Project FT047 — Battery in Tooele, Utahnew_project—active
2026-11-16PACE Queue Project T2-071 — Solar+Battery in San Juan, Utahstatusactivewithdrawn
2026-11-16PACE Queue Project T2-039 — Solar+Battery in Emery, Utahstatusactivewithdrawn
2026-11-16PACE Queue Project T2-037 — Solar+Battery in Emery, Utahstatusactivewithdrawn
2026-11-16PACE Queue Project C1-51 — Solar+Battery in Juab, Utahstatussuspendedactive
2026-11-16PACE Queue Project C1-16 — Solar+Battery in Millard, Utahstatussuspendedactive
2026-11-01Faraday Energy Storageoperational_date—2026-09-01
2026-11-01Faraday Energy Storageproposed_online_date2026-09-01—
2026-11-01Faraday Energy Storagestatusactiveoperational
2026-11-01Cape Generating Stationoperational_date—2026-09-01

Explore related data

Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: bpa-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); idahopower-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; pacificorp-oasis; wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get notified when a new project appears in Utah.

Start tracking with interXdata