Milford Upgrades - Phase I (533)

Milford Upgrades - Phase I is a 16.6 MW gas interconnection project in New Haven, Connecticut with a current status of operational. It is proposed to connect at 115kV East Devon Substation.

16.6 MWCapacity
OperationalStatus
SWCTMarket
GasTechnology

Project facts

Canonical nameMilford Upgrades - Phase I
Queue ID533
Statusoperational
Source statusC
MarketSWCT
TechnologyGas
Capacity16.6 MW
StateConnecticut
CountyNew Haven
Point of interconnection115kV East Devon Substation
Requested (queue) date2015-02-27
Proposed in-service date
Operational date2017-06-05
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata