Mineral Springs BESS (26INR0499)

Mineral Springs BESS is a 104.0 MW other interconnection project in Burnet, Texas with a current status of operational. It is proposed to connect at 7065 DOBVI 138kV.

104.0 MWCapacity
OperationalStatus
BurnetMarket
OtherTechnology

Project facts

Canonical nameMineral Springs BESS
Queue ID26INR0499
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketBurnet
TechnologyOther
Capacity104.0 MW
StateTexas
CountyBurnet
Point of interconnection7065 DOBVI 138kV
Requested (queue) date2024-06-03
Proposed in-service date
Operational date2027-11-02
Withdrawn date
DeveloperBurnet County LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.