Miranda Solar Project (24INR0161)

Miranda Solar Project is a 202.0 MW solar interconnection project in McMullen, Texas with a current status of operational. It is proposed to connect at Tap 345kV 5709 Fowlerton - 5901 San Miguel Ckt 1.

202.0 MWCapacity
OperationalStatus
McMullenMarket
SolarTechnology

Project facts

Canonical nameMiranda Solar Project
Queue ID24INR0161
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketMcMullen
TechnologySolar
Capacity202.0 MW
StateTexas
CountyMcMullen
Point of interconnectionTap 345kV 5709 Fowlerton - 5901 San Miguel Ckt 1
Requested (queue) date2021-11-03
Proposed in-service date
Operational date2027-12-06
Withdrawn date
DeveloperMiranda Solar Project, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.