MISO Queue Project G507 — Wind in Fond Du Lac, Wisconsin

MISO Queue Project G507 — Wind in Fond Du Lac, Wisconsin is a 68.0 MW wind interconnection project in Fond Du Lac, Wisconsin with a current status of operational. It is proposed to connect at Near intersection of 138kV line X-2 (OHM-MUR), 345kV line W-1 (SFL-EDG), and 345kV line 971L51 (FJT-ADN).

68.0 MWCapacity
OperationalStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G507 — Wind in Fond Du Lac, Wisconsin
Queue IDG507
Statusoperational
Source statusoperational
MarketMISO
TechnologyWind
Capacity68.0 MW
StateWisconsin
CountyFond Du Lac
Point of interconnectionNear intersection of 138kV line X-2 (OHM-MUR), 345kV line W-1 (SFL-EDG), and 345kV line 971L51 (FJT-ADN)
Requested (queue) date2005-03-11
Proposed in-service date2005-11-01
Operational date2005-11-01
Withdrawn date
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.