MISO Queue Project G712 — Coal in Bowman, North Dakota

MISO Queue Project G712 — Coal in Bowman, North Dakota is a 513.0 MW coal interconnection project in Bowman, North Dakota with a current status of withdrawn. It is proposed to connect at existing unnamed 230 kV transmission line 2 miles south of plant.

513.0 MWCapacity
WithdrawnStatus
MISOMarket
CoalTechnology

Project facts

Canonical nameMISO Queue Project G712 — Coal in Bowman, North Dakota
Queue IDG712
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyCoal
Capacity513.0 MW
StateNorth Dakota
CountyBowman
Point of interconnectionexisting unnamed 230 kV transmission line 2 miles south of plant
Requested (queue) date2006-12-11
Proposed in-service date2012-10-01
Operational date
Withdrawn date2008-12-01
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.