MISO Queue Project G980 — Wind in Hettinger, North Dakota is a 60.0 MW wind interconnection project in Hettinger, North Dakota with a current status of withdrawn. It is proposed to connect at New substation tapped into MDU 115 kV line at N46 36 53/W102 46 12.
Project facts
| Canonical name | MISO Queue Project G980 — Wind in Hettinger, North Dakota |
|---|---|
| Queue ID | G980 |
| Status | withdrawn |
| Source status | withdrawn |
| Market | MISO |
| Technology | Wind |
| Capacity | 60.0 MW |
| State | North Dakota |
| County | Hettinger |
| Point of interconnection | New substation tapped into MDU 115 kV line at N46 36 53/W102 46 12 |
| Requested (queue) date | 2008-03-10 |
| Proposed in-service date | 2011-12-31 |
| Operational date | — |
| Withdrawn date | 2010-03-26 |
| Developer | — |
| Utility / transmission owner | MISO |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata