MISO Queue Project H004 — Gas in Eau Claire, Wisconsin

MISO Queue Project H004 — Gas in Eau Claire, Wisconsin is a 860.0 MW gas interconnection project in Eau Claire, Wisconsin with a current status of withdrawn. It is proposed to connect at Eau Claire 345 kV Substation.

860.0 MWCapacity
WithdrawnStatus
MISOMarket
GasTechnology

Project facts

Canonical nameMISO Queue Project H004 — Gas in Eau Claire, Wisconsin
Queue IDH004
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyGas
Capacity860.0 MW
StateWisconsin
CountyEau Claire
Point of interconnectionEau Claire 345 kV Substation
Requested (queue) date2008-04-14
Proposed in-service date2009-12-31
Operational date
Withdrawn date2009-05-14
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata