MISO Queue Project J532 — Solar in Cass, Iowa

MISO Queue Project J532 — Solar in Cass, Iowa is a 50.0 MW solar interconnection project in Cass, Iowa with a current status of withdrawn. It is proposed to connect at Red Oak √¢‚Ǩ‚Äú Coburg 69kV Line.

50.0 MWCapacity
WithdrawnStatus
MISOMarket
SolarTechnology

Project facts

Canonical nameMISO Queue Project J532 — Solar in Cass, Iowa
Queue IDJ532
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologySolar
Capacity50.0 MW
StateIowa
CountyCass
Point of interconnectionRed Oak – Coburg 69kV Line
Requested (queue) date2015-11-16
Proposed in-service date2016-09-01
Operational date
Withdrawn date2016-02-17
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.