Mississinewa-Gaston 138 kV (AE2-172)

Mississinewa-Gaston 138 kV is a 40.0 MW battery interconnection project in Grant, Indiana with a current status of suspended.

40.0 MWCapacity
SuspendedStatus
—Market
BatteryTechnology

Project facts

Canonical nameMississinewa-Gaston 138 kV
Queue IDAE2-172
Statussuspended
Source statusSuspended
Market—
TechnologyBattery
Capacity40.0 MW
StateIndiana
CountyGrant
Point of interconnection—
Requested (queue) date2019-03-16
Proposed in-service date2026-05-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—suspendedhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.