Moonlight Flats Solar (C24-301)

Moonlight Flats Solar is a 250.0 MW solar interconnection project in Clearfield, Pennsylvania with a current status of active. It is proposed to connect at Homer City 345 kV to Mainesburg 345 kV L47.

250.0 MWCapacity
ActiveStatus
CMarket
SolarTechnology

Project facts

Canonical nameMoonlight Flats Solar
Queue IDC24-301
Statusactive
Source status6
MarketC
TechnologySolar
Capacity250.0 MW
StatePennsylvania
CountyClearfield
Point of interconnectionHomer City 345 kV to Mainesburg 345 kV L47
Requested (queue) date2024-09-30
Proposed in-service date
Operational date
Withdrawn date
DeveloperMoonlight Flats Solar Power, LLC
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata